Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
FBO DAILY - FEDBIZOPPS ISSUE OF DECEMBER 08, 2016 FBO #5494
MODIFICATION

Z -- The work consists of providing all labor, materials, and equipment, as required to repair 1650 square feet of brick mortar joints at Station Shark River located at 125 Washington Lane Avon by the Sea, NJ 07717.

Notice Date
12/6/2016
 
Notice Type
Modification/Amendment
 
NAICS
238140 — Masonry Contractors
 
Contracting Office
Department of Homeland Security, United States Coast Guard (USCG), USCG Training Center (TRACEN) Cape May, 1 Munro Avenue, Mission Support Building, Room 212A, Cape May, New Jersey, 08204-5092, United States
 
ZIP Code
08204-5092
 
Solicitation Number
HSCG27-17-Q-5CV080
 
Archive Date
1/25/2017
 
Point of Contact
christopher j. moulton, Phone: 6098986276
 
E-Mail Address
christopher.j.moulton@uscg.mil
(christopher.j.moulton@uscg.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
SCOPE OF WORK 1. GENERAL REQUIREMENTS: The work consists of providing all labor, materials, and equipment, as required to repair 1650 square feet of brick mortar joints at Station Shark River located at 125 Washington Lane Avon by the Sea, NJ 07717. 2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: Upon acceptance, the Contractor shall commence work NLT one hundred twenty (120) days after notice to proceed, and work diligently to complete the entire project to be ready for use NLT one hundred fifty (150) working days after contract award. 3. SCOPE OF WORK: 1) Clean Existing 1,650 square ft. Brick Veneer, (building is 15ft at highest point). 2) Remove loose mortar to the industry recommended depth based on condition found around the entire building and clean out remaining dust or debris. 3) Match mortar to brick type using ASTM C 270 and ASTM C 1357. 4) Mortar shall be properly mixed in accordance with ASTM C 1586. 5) Re-point approximately 6,100 linear ft. of mortar joints. 6) Re-pointing should not be completed when temperature is under 40°F or above 100°F 7) Remove existing caulking around (6) 3'x 5', (1) 3'x 3' windows, (1) 36"x 80"door, and (1) 16'x10' garage door. 8) Apply new caulking around windows and doors in accordance with Manufactures instructions. 4. SITE VISIT: All bidders are strongly encouraged to visit the site to verify any/all quantities before submitting bids. Interested parties shall make arrangements for a site visit with MKC Robert Panish @ (732) 899-0130. 5. DESIGNATED CONTRACTING OFFICER'S QA EVALUATOR (QAE) REPRESENTATIVE: The designated Contracting Officer's QAE representative and Point of Contact for their project is MKC Robert Panish @ (732) 899-0130. Inquiries concerning any phase of the specification before or after award shall be made to CWO3 Louis Bevilacqua @ (609) 677-2173. 6. CONDITIONS AFFECTING THE WORK: The Offeror should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, the general and local conditions which can affect the cost of the work thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The Government will assume no responsibility for any understanding or misrepresentations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the request for quotes, the specification or related documents. 7. AFTER AWARD OF THE CONTRACT: The Contractor must immediately notify the Contracting Officer's QAE representative of their intended start date. The work shall be done in accordance with the specification. 7.1. The Contractor shall consider items in BOLD as having mandatory due dates. Items in italics are deliverables or events that must be reviewed and/or approved by the QAE prior to proceeding to next deliverable or event in this SOW. SEE FULL AMENDED (1) SOW FOR DATES. 8. ORAL MODIFICATION: No oral statement of any person other than the Contracting Officer shall in any manner or degree, modify or otherwise affect the terms of the contract. 9. WORKMANSHIP: All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer. 9. WORKMANSHIP: All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer. 10. PERMITS: The Contractor shall without additional expense to the Government, obtain all appointments, licenses, and permits required for the prosecution of the work. The Contractor shall comply with all applicable federal, state, and local laws. 11. CLEAN UP: All trash and debris shall be removed from the site daily. The job site shall be left in a clean and neat manner. 12. WORK OUTSIDE REGULAR HOURS: If the Contractor desires to carry on work on Saturday, Sunday, holidays, or outside the unit's regular hours, a written request must be submitted to the Contracting Officer's QAE Representative for approval consideration. The Contractor shall allow ample time to enable satisfactory arrangements to be made by the Government for inspecting the work in progress. 13. UPON COMPLETION OF WORK: Contact the Contracting Officer's QAE Representative to arrange for inspection/acceptance of work. 14. IDENTIFICATION OF CONTRACTOR PERSONNEL AND VEHICLES: The Contractor shall provide a detailed list of all employees to the QAE Representative five (5) days prior to commencing work. The employee list shall contain the employee's full name, date and place of birth, current address, and last four (4) of SSN. The Station Shark River Security Officer will be given a copy of the employee list and grant access for entry. Each Contractor provided vehicle or towed trailer shall show the Contractor's name so that it is clearly visible on the vehicle. A valid state license plate and safety inspection sticker is required. All vehicles operated on Government property shall be maintained in a good state of repair. 15. SAFETY REQUIREMENTS: 1. Responsibilities: a. All Contractors working on CG Station Shark River shall abide by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series) and 29 CFR 1926 (series). Contractor written safety programs shall be reviewed by the Safety Officer prior to starting work. b. Written notification must be provided to the Station Shark River Safety Officer, MKC Robert Panish @ (732) 899-0130 in their capacity as Fire Marshal of any activity that could potentially cause fire or explosion or that change or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are: A fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the unit, and blocking of any egress routes or emergency vehicle routes. Inclusion of their information in the contract constitutes written notification as long as the outsource review sheet is signed by Safety Officer. c. Copies of the following must be provided to the Safety Officer prior to starting work in affected areas: Confined Space Entry Permits, Hot Work Chits, and Dig Chits. Confined space clearance must be conducted by a certified marine chemist and permit required spaces will have a copy of the permit posted on site during work. Hot work will only be conducted with permission and a fire watch must be posted during work. d. Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a Contractor on Station Shark River. A Facilities Division representative is required for all Contractor Lock Out/Tag Out needs and shall be coordinated by the Safety Officer listed above. 2. Rights: a. Every employee working on Station Shark River has the right to a safe and healthy work place. The Contractor has the responsibility and right to stop unsafe work. QAE's and the Safety Officer may also institute a work stoppage relating to unsafe practices or immediate danger to life and health situations. 16. ENVIRONMENTAL PROTECTION REQUIREMENTS: a. All Contractors working on Station Shark River shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40 CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist MKC Robert Panish @ (732) 899-0130, prior to starting work and must be in accordance with the Unit Environmental Guide. b. Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on Station Shark River Some examples of qualifying activities are: any activity that could result in a spill, discharge into a waterway, or introducing a hazardous material into the environment. c. Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas: Material Safety Data Sheets, permits, and notices of intent. d. Hazardous materials used by a Contractor are required to be disposed of by that Contractor. Disposal must be in accordance with federal, state, and local guidelines. 6DEC2016: Changes dates for period of performance. Changed package due date to 23DEC2016 at 1400 EST.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/DHS/USCG/COUSCGTCCM/HSCG27-17-Q-5CV080/listing.html)
 
Place of Performance
Address: Station Shark River, 125 Washington Lane Avon by the Sea, NJ 07717, AVON BY THE SEA, New Jersey, 07717, United States
Zip Code: 07717
 
Record
SN04344919-W 20161208/161206235614-ab3391bd755687b530eb6e47579844ed (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  © 1994-2020, Loren Data Corp.