Z -- Nez Perce-Clearwater NFs - Teepee Spring BAER Culvert Replacements NFSR 221 and 263

Notice Date
7/1/2016
 
Notice Type
Presolicitation
 
NAICS
237990 — Other Heavy and Civil Engineering Construction
 
Contracting Office
Department of Agriculture, Forest Service, R-1 IMAT: Clearwater; Idaho Panhandle; Kootenai; and Nez Perce NF's, 3815 Schreiber Way, Coeur d'Alene, Idaho, 83815-8363, United States
 
ZIP Code
83815-8363
 
Solicitation Number
AG-0343-S-16-0065
 
Point of Contact
Karen Ruklic, Phone: 208-983-5144
 
E-Mail Address
kruklic@fs.fed.us
(kruklic@fs.fed.us)
 
Small Business Set-Aside
HUBZone
 
Description
Description of Work: The project consists of removing multiple 18 inch and one 24 inch culvert and replacing them with corrugated steel pipe culverts and pipe arches at multiple locations on NFSR 221 and NFSR 263 to accommodate post fire flow. The pipe arches will be government furnished. NFSR 221: The intent of the contract is to remove and replace three existing corrugated steel pipe culverts on NFSR 221 at mile posts 54.73, 55.03, and 65.16. NFSR 263: The intent of the contract is to remove and replace seven existing corrugated steel pipe culverts on NFSR 263 at mile posts 2.37, 2.41, 3.167, 3.60, 4.90, 6.78, and 7.29. This project includes removing and disposing an existing culvert, structure excavation, roadway embankment, backfilling, compacting, furnishing and installing a new corrugated steel pipe, riprap, and hauling and placing crushed aggregate surfacing. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract. Project Location: This project is located in the Nez Perce-Clearwater National Forests approximately 45 miles south on Hwy 95, 11 miles East on Big Salmon Rd on NFSR 221. On NFSR 221 work will start at approximately MP 54 and ending at MP 66, and NFSR 263 starting at Mile Post 0 and ending at mile post 8 in the Salmon River Ranger District. T24 N and T25N; R. 2 E; Idaho County, Idaho. Price Range: The Government's estimate for the project is between than $250,000 and 500,000. Pre-Bid Tour: None planned Period of Performance and Road Closure Restrictions: Work on the project site shall commence approximately September 1, 2016, and proceed in accordance with the contractor's approved work schedule and run continuously till the end of the project no later than October 15, 2016. Closure of FS Road 263 will be allowed between 9/1/2016 and 9/21/2016 to facilitate culvert replacement activities. Closure of FS Road 221 in the vicinity of MP 65.16 will be allowed between 9/26/16 and 10/5/16. Closure of FS Road 221 in the vicinity of Mile Posts 54.73 and 55.03 will be allowed for two weeks between 9/1/16 and 10/5/16. Contractor shall give 10 days notice prior to closing this section of road.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USDA/FS/281/AG-0343-S-16-0065/listing.html)
 
Place of Performance
Address: Nez Perce-Clearwater National Forests, Grangeville Office, 104 Airport Road, Grangeville, Idaho, 83530, United States
Zip Code: 83530
 
Record
SN04169440-W 20160703/160701233858-e800544d0dca2eb6586b724668ca3872 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  © 1994-2020, Loren Data Corp.