Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
FBO DAILY ISSUE OF OCTOBER 21, 2005 FBO #1425
MODIFICATION

99 -- STORMWATER STORAGE TANKS

Notice Date
10/19/2005
 
Notice Type
Modification
 
Contracting Office
Environmental Protection Agency, Ow Service Center, 26 West Martin Luther King Drive, Cincinnati, OH 45268
 
ZIP Code
45268
 
Solicitation Number
RFQ-OH-06-00002
 
Response Due
10/26/2005
 
Archive Date
11/26/2005
 
Description
NAICS Code: 339999 Amendment #3 Technical Questions Question #1: If the tanks are to be partially buried, why are you asking for saddle supports for the tanks? Answer: The Fed Biz Ops announcement does not mention or require saddle supports. Question #2: Fiberglass tanks cannot be partially buried, they must be fully buried, so if we use steel tanks, must they have an internal coating or lining? Answer: The portion of the tank that contacts the stored water must not leach chemicals into the stored water. For example, the EPA is currently using a PE flexible liner within a galvanized steel structural member, similar to an above-ground back-yard swimming pool. In other applications the EPA is currently using self-supporting tanks made entirely of PE. Question #3: Because of Hurricane Katrina and the steel availability problems, it is doubtful that these tanks, in any quantity could be delivered in 4 weeks. Answer: If you are unable to meet the delivery schedule, please note the delivery schedule that you can meet. Delivery time will be a consideration for award, as stated in the Fed Biz Ops Specifications. (1) Technical acceptability of the item offered to meet the Government's requirement and (2) Technical acceptability shall be evaluated on a pass or fail basis (with the lowest price technically acceptable receiving award). Delivery time is part of the specifications for this requirement. Question #4: Can the EPA confirm the number and size of the openings you need, as well as the manhole on the top of the tank centerline that you need? Answer: There are no man-holes described in the RFQ. The EPA will install the openings in the small stormwater tanks. The supplier must provide directions for installing the pipe connections and cutting the overflow weir (as stated in the Fed Biz Ops Specifications. The internal tank of the nested tank pair requires a bottom opening that will accept a 1 1/2-inch (minimum) PVC pipe, as also stated in the Fed Biz Ops Specifications. The last date for technical questions for this requirement is October 21, 2005. Amendment #2 Technical Questions Question #1: Can we assume all of the tanks can be double walled and fiberglass? Answer: Double walled and fiberglass is acceptable, but not required. Question #2: Can we assume the nested tanks are two tanks fixed together that work independently of each other and the EPA wants four sets totaling eight tanks, and the minimum pipe diameter is one (1) inch in each tank? Answer: The tanks are set of two (eight total tanks). The minimum pipe diameter is 1 ? inches, 1 inch is not acceptable? Question #3: Will the tank flushing or cleaning be conducted without a clean-out opening or access port? Answer: The tanks must have an open top (not sealed). Amendement #1 Technical Questions Question #1: The Fed Biz Ops announcement states that the tanks will be "partially buried". What exactly does that mean Are the tanks going to be buried 1/4 or 1/2 way up, or what specifically? Answer: The Burial depth will vary from tank to tank. Typically from 25% to 75% of total tank height will be below grade. Stormwater Storage Tanks This is a combined synopsis/request for quote for commercial items prepared in accordance with the format in FAR Subpart 12.6, as supplemented with additional information included in this notice. Quotes are being requested and a written RFQ will not be issued. Shipping charges need to be included in price. The NAICS code is 339999. The specifications for the Stormwater Storage Tanks are as follows: Stormwater Storage Tanks 1.0 Background The EPA is procuring 27 storage tanks of various sizes and capacities. The tanks will be used to hold stormwater for experimental research projects. The portion of the tanks in contact with the held stormwater must not leach additional chemicals into the stormwater. Smooth interiors must be provided to assure the EPA's ability to clean the tanks between uses. The tanks will be partially or mostly buried in sandy soil/crushed concrete. The EPA anticipates the tanks will be required for at least five (5) years after installation. The tanks are necessary for the EPA to support the on-going stormwater research work, related to best management practices. 2.0 Tank Specifications and Requirements The EPA requires a series of stormwater storage tanks. The type and quantity are outlined below: Item 1: Stormwater storage tanks (13) The tanks shall be circular or oval in horizontal cross section with larger axis no grater than 10 feet. Interior surfaces shall be constructed of a non-leaching material. Exterior support may be of another material. If metal, the support shall be galvanized steel with at least 15-gauge thickness. Single piece construction or on-site assembly by the EPA is acceptable. If not assembled by the contractor, the contractor shall provide written assembly directions. The storage capacity shall be at least 1000 gallons. The EPA requires thirteen (13) tanks of this size. The tanks will be partially buried upon installation in a sandy soil. Item 2: Small stormwater tanks (4) The tanks shall have rectangular horizontal cross section and be constructed of non-leaching plastic material (e.g., polyethylene, fiberglass). Tanks must accommodate stormwater (flow-through) storage with nominal capacity of 75 to 150 US gallons. Longer horizontal dimension must be 80 to 100 inches. The tank material must allow field drilling and cutting to install bottom feed pipe and overflow weir. The EPA requires four (4) tanks of this size. These tanks are will be partially buried in crushed concrete. All tanks must arrive fully assembled other than the pipe connection and weir, which will be installed by the EPA. Tanks must provide written direction for connection of piping through the tank walls and notching for installation of the weir. Item 3: Large stormwater storage tanks (2) The tanks shall be circular or oval in horizontal cross section with larger axis no greater than 35 feet. Interior surfaces shall be constructed of a non-leaching material (e.g., polyethylene). The exterior support may be of another material. If metal, the support shall be galvanized steel with at least 15-gauge thickness. Single piece construction or on-site assembly by the EPA is acceptable. If not assembled by the contractor, the contractor shall provide written assembly directions. The storage capacity shall be at least 15,000 gallons. The EPA requires two (2) tanks of this size. The tanks will be partially buried upon installation in a sandy soil. Item 4: Nested tanks (8) The tanks shall be circular in horizontal cross section and be constructed of a non-leaching material (e.g., polyethylene). Smaller inner tank must have a minimum area of 30 square feet with conical bottom and center drain which will accept PVC pipe connections. The minimum pipe diameter is 1 ? inches. The outer tank must have a depth of at least 4 inches greater than the inner depth and a diameter at least 4 inches larger than inner tank. The outer tanks will be partially buried upon installation in a sandy soil. The inner tank must nest within the outer tank. The EPA requires four (4) sets of nested tanks. Tanks must arrive fully assembled. 3.0 Calibration and Testing Not applicable 4.0 Documentation and Drawings The contractor shall specify the material of construction as part of the quotation. The contractor shall include assembly directions as needed. 5.0 Warranty For each tank the contractor shall provide a commercial warranty of at least 90 days for all parts, labor, and materials. Tanks shall be warranted as appropriate for partially buried installation as described in each item. Tanks shall be warranted as lead free for the duration of the warranty. 6.0 Delivery Date The completed system shall be delivered no later than 30 days after receipt of award to U.S. EPA, 2890 Woodbridge Ave., Edison NJ 08837. FOB point shall be destination. The following clauses apply to this request for quote: FAR 52.212-1, Instructions to Offerors-Commercial Items; FAR 52.212-2 Evaluation-Commercial Items, and the specific evaluation criteria is as follows: (1) Technical acceptability of the item offered to meet the Government's requirement and (2) Technical acceptability shall be evaluated on a pass or fail basis (with the lowest price technically acceptable receiving award). Offers shall provide descriptive technical literature and other documentation as necessary, in sufficient detail to demonstrate that the items offered meet the minimum requirements specified above; FAR 52.212-3, Offeror Representations & Certifications-Commercial Items, shall be completed by offeror and submitted with quote, unless the offeror's registered with CCR; FAR 52.212-4, Contract terms & Conditions-Commercial Items; The following FAR clauses in paragraph (b) of FAR clause 52.212-5, Contract Terms & Conditions Required to Implement Statutes or Executive Orders-Commercial Items will apply, 52.222-3, 52.222-19, 52.222-21, 52.222-26, 52.222-35, 52.222-36, 52.222-37, 52.222-3, 52.225-13. FAR 52-225-1, Buy American Act-Supplies; FAR 52.232-33, Payment by Electronic Funds Transfer-Central Contractor Registration; all clauses can be found at: http://farsite.hill.af.mil/VFFARA.HTM. Offers shall submit 1 copy of their quotation that references RFQ-OH-06-00002, no later than Wednesday October 26, 2005 at 3:00 PM (EST) to Scott A. Fogle, at fogle.scott@epa.gov or via fax at 513 487-2107. Questions or comments may also be directed to Scott A. Fogle, at 513 487-2049, or at fogle.scott@epa.gov.
 
Record
SN00918038-W 20051021/051019212213 (fbodaily.com)
 
Source
FedBizOpps.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  © 1994-2020, Loren Data Corp.