SOURCES SOUGHT

Y -- Construction of 31,268'' of overhead and 22,336'' of underground electrical distribution lines at Avon Park AFR, Fl.

Notice Date
7/16/2003
 
Notice Type
Sources Sought
 
Contracting Office
Department of the Air Force, Air Mobility Command, 6th Contracting Squadron, 2606 Brown Pelican Ave., MacDill AFB, FL, 33621-5000
 
ZIP Code
33621-5000
 
Solicitation Number
F08602-03-R-0015
 
Response Due
7/23/2003
 
Archive Date
8/7/2003
 
Point of Contact
Kenneth Huckins, Contract Specialist, Phone 813-828-7483, Fax 813-828-3667,
 
E-Mail Address
huckinsk@macdill.af.mil
 
Description
Beginning at Peace River Electric Cooporative (PRECO) pole #30-1-96 located at Tango Site radio tower, build 2.6 miles of overhead, single-phase, 2#2ACSR. 7.2kV power line east paralleling Kissimmee Road. Typical pole size will be 40-5; span lengths will be 375'. Also associated with the overhead construction is 30 man-hours of right-of-way trimming. Construction paralling Kissimmee Road ends at the grade to Charlie Range. Begin at intersection of Kissimmee Road and grade to Charlie Range; build south paralleting Charlie grade 1,200' using 2#2ACSR, 7.2kV overhead power line. Typical ploe size will be 40-5; span lengthd will be 400'. Begin at the end of new overhead construction on Charlie grade and construct 1.2 miles of 1/0 25kV underground primary power line to pad mounted, 15kVa transformer with 1/0 underground service wire to north tower at Charlie Range. This work includes one (1) directional bore of 200' under a culvert. Begin at the north tower of Charlie Range and proceed south, paralleling Charlie grade for 4,000' using 1/0 25kV underground primary power line to pad mounted 15kVa transformer with 1/0 underground service wire to Charlie Range Tower. COntinue underground construction from center tower for 4,000' to southern tower. Ending phase I. Phase II. Begin at PRECO pole #30-55-9 located at the Natural Resources Warehouse, building 601, Build 16,340' pf overhead primary power line using 2 #2ACSR, 7.2kV, paralleling H.R. Smith Grade. Typical pole size will be the same as aforementioned. Span lengths 376'. Overhead line extension to end of southeast Brave Right Flank Tower with overhead transformer with 1/0 underground electrical service to tower. Begin at the southeast Brave tower and biuld 4,000' of single-phase, 1/0 25kV underground primary power line to pad mounted transformer with 354 MCM underground service wire to Bravo Center Tower. Proceed northwest from Bravo cneter tower 4,000' of single-phase 1/0 25kV underground primary power line to pad mounted transformer with 1/0 underground service to northwest Bravo tower. End of Phase II.
 
Place of Performance
Address: Avon Park AFR, Fl
Country: USA
 
Record
SN00372892-W 20030718/030716213618 (fbodaily.com)
 
Source
FedBizOpps.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.